A strip-out scheduled for Monday can come unstuck well before the first wall lining is removed. If asbestos is identified on Friday, the required notice period, licence class and control measures may make a Monday start unrealistic. Understanding Victoria asbestos notification requirements early helps property owners, builders and facility managers avoid unsafe work, project delays and compliance problems.

When is asbestos removal notification required in Victoria?

In Victoria, notification to WorkSafe is generally required before licensed asbestos removal work begins. This includes any friable asbestos removal, regardless of quantity, and non-friable asbestos removal where the area is more than 10 square metres.

Friable asbestos is material that can be crumbled, pulverised or reduced to powder by hand pressure when dry. It is commonly found in pipe lagging, insulation, sprayed coatings and some fire-rated materials. Because fibres can be released more readily, friable asbestos work requires the highest level of control and a Class A asbestos removal licence.

Non-friable asbestos is bonded within a solid material, such as asbestos cement sheeting, corrugated roofing, fencing, vinyl floor tiles or eaves. A Class B licence may be required for removal of more than 10 square metres of non-friable asbestos-containing material. Small-scale work below that threshold does not automatically mean it is safe for an unlicensed person to proceed. The material’s condition, location, method of removal and likelihood of fibre release all matter.

A competent assessment before work starts is the sensible first step. In older Melbourne and Victorian properties, asbestos can be present in places that are easily disturbed during renovation or demolition, including bathrooms, kitchens, roofs, subfloors, service ducts and external cladding.

Victoria asbestos notification requirements: allow the full notice period

For licensed asbestos removal, the licensed removalist must provide written notification to WorkSafe Victoria at least five days before removal work starts. This is a planning requirement, not paperwork to leave until the site is already set up.

The notification should accurately set out the location of the work, the planned dates, the asbestos material involved, the type and amount of asbestos, and the licence details of the removalist. WorkSafe needs enough information to understand what is being removed and where the work will occur.

The five-day period can affect demolition programs, tenancy handovers and renovation schedules. It is particularly relevant where asbestos is only discovered after demolition has commenced. Stopping work, securing the area and arranging a proper assessment may be frustrating, but it is far safer and more cost-effective than continuing with unknown material.

If dates, scope or site details change after notification, do not assume the original notice still covers the work. The licensed removalist should review the notification and advise WorkSafe of changes as required. Good project management means allowing a contingency for asbestos, especially in buildings constructed before asbestos use was phased out.

There can be different arrangements for genuine emergencies, such as damage from a fire, storm or other incident that creates an immediate risk. An urgent situation is not simply a tight construction deadline. The area should be isolated and professional advice obtained before removal starts.

A notification is not permission to take shortcuts

Lodging a notification does not replace the other duties that apply to asbestos work. The removalist must still use the appropriate licence, prepare and follow an asbestos removal control plan, establish exclusion zones, use suitable decontamination arrangements and package, transport and dispose of waste correctly.

For occupied workplaces, there may also be consultation duties with employees, contractors, health and safety representatives, tenants or other people who could be affected by the work. The right communication depends on the site, but people should know where the work is occurring, when access is restricted and what controls are in place.

Licensing depends on the material and scope

The licence requirement is one of the most common points of confusion. A Class A asbestos removal licence is required for friable asbestos and permits removal of both friable and non-friable asbestos. A Class B licence permits removal of non-friable asbestos above the relevant threshold, but not friable asbestos.

For a homeowner, this may sound like a contractor issue. In practice, it is a client risk as well. Engaging an appropriately licensed and insured removalist helps protect the household, neighbours, trades and the property owner. It also gives builders and facility managers a clear compliance trail for their project records.

Before appointing a contractor, confirm the material has been properly identified, ask what licence class applies, and make sure the quoted scope includes waste transport and lawful disposal. A cheap quote that only covers removing sheets from a wall can become expensive if it leaves out containment, clearance, cleaning or waste management.

Notification sits within a wider asbestos management process

A sound asbestos job starts before notification. Where the building is a workplace, an asbestos register may already identify known or presumed asbestos-containing materials. For older buildings without reliable records, an asbestos audit or targeted sampling can identify the risk before a builder cuts into linings, removes flooring or starts demolition.

Once asbestos is confirmed, the removal method should suit the material and environment. A small section of bonded eave sheeting on a vacant house needs different controls from friable pipe insulation in an operating commercial plant. Access routes, nearby occupants, electrical services, weather exposure, traffic movements and the condition of the material all affect the plan.

The work area should be clearly controlled so fibres are not carried into clean areas. Depending on the job, this can include barriers, warning signage, restricted access, wet methods, suitable personal protective equipment, decontamination procedures and careful cleaning with the correct equipment. Breaking asbestos sheets unnecessarily, using power tools without proper controls or dry sweeping debris can turn a manageable removal into a contamination event.

After removal, the site needs to be checked before normal access resumes. Independent clearance inspection and certification may be required for licensed asbestos removal work, particularly where friable asbestos has been removed. The clearance process confirms that the area has been cleaned and is safe to hand back in line with the work performed.

Common mistakes that cause delays and added cost

The most avoidable asbestos issues are usually planning failures rather than difficult removal work. Watch for these problems:

  • Starting demolition before an asbestos assessment. Hidden materials are often found once walls, ceilings or floor coverings are opened up.
  • Assuming all cement sheeting is safe because it looks intact. Visual checks alone cannot confirm whether a material contains asbestos.
  • Treating a five-day notice period as a contractor-only concern. It can directly change the construction program, access arrangements and tenant communications.
  • Using a quote that does not clearly state the scope. Clarify sampling, notification, removal controls, waste disposal, clearance and final cleaning before work begins.

There is also a practical distinction between removing material and managing material in place. If asbestos is in good condition and unlikely to be disturbed, removal may not always be the best immediate option. Encapsulation, labelling, monitoring and updating the asbestos register can sometimes be appropriate. That decision should be based on the condition of the material, planned works and future access, not guesswork.

What builders and site managers should do when asbestos is found unexpectedly

Stop the work in the affected area straight away. Keep workers and other people out, prevent further disturbance and avoid attempting to clean up debris with ordinary tools or household equipment. Take enough details to identify the location and condition of the material, then arrange an assessment by a competent asbestos professional.

If the material is confirmed or presumed to contain asbestos, the next steps can be planned properly: determine whether licensed removal is required, prepare the removal control plan, make the required WorkSafe notification and coordinate the work around the site program. This response protects people first and gives the project the best chance of getting back on track without creating a larger contamination issue.

For commercial, industrial and government sites, document the discovery, controls and decisions taken. This assists with duty-of-care obligations and ensures every contractor working nearby receives consistent information. It is also useful evidence if the scope, timing or cost of the project later needs to be explained.

Get the advice before the job is committed

Asbestos compliance is easier when the assessment, notification and removal plan are organised as one process rather than separate jobs. Asbestos Audits Australia provides practical advice and licensed asbestos services across Melbourne and Victoria, with a focus on safe work, clear communication and high-quality workmanship.

If a planned renovation, demolition or maintenance job could disturb older building materials, allow time to identify the risk before trades are booked. A short conversation and a professional assessment at the start can prevent a rushed decision when the site is already open.